516 F.Supp. 1085
ROBERT E. DERECKTOR
OF RHODE ISLAND, INC., et al., Plaintiffs, OPINION FRANCIS J. BOYLE, District Judge. The issue in this action is the validity of an award to Plaintiffs, Robert E. Derecktor of Rhode Island, Inc. and Rhode Island Ship Builders, Inc., (hereinafter Plaintiff), by Defendant Coast Guard of a contract to construct nine 270 foot, 1700 ton medium endurance cutters and to provide spare parts at a bid price of $349,000,000.00. Plaintiff brought the action because the Coast Guard initially determined both it as the lowest bidder and Intervenor Marine Power as the second lowest bidder to be nonresponsive bidders and awarded the contract to Intervenor Tacoma Boatbuilding, the third lowest bidder for a price of $391,882,517 on August 28, 1980. By Opinion in Robert E. Derecktor of Rhode Island, Inc. v. Goldschmidt, 506 F.Supp. 1059 (D.R.I.1980), this Court declared the Coast Guard's determination of nonresponsiveness to be invalid, and, on January 15, 1981, the Coast Guard awarded the contract to Plaintiff. Intervenors Marine Power and Tacoma (hereinafter sometimes Intervenors) now contend that award to Plaintiff is invalid, is contrary to procurement regulations and that Plaintiff is not a responsible bidder. . . . . Defendant Coast Guard requested
bids to construct much needed cutters to replace outmoded vessels presently
in use, to be opened in June, 1980. Six bids were submitted. The bids
were: Derecktor
$349,530,719 Marine
$380,854,103 Tacoma
$391,882,517 When the Coast Guard determined the Derecktor bid to be responsive, it was then necessary in accord with procurement regulations to determine if Derecktor was also a responsible bidder. 41 C.F.R. s 1-2.407-2. A preaward survey team was appointed by the contracting officer. Captain James E. Grabb was appointed Chairman, and the other members were Captain H. E. Fallon, Commander J. D. Vitkauskas, Lieutenant Commander J. W. Hall, Lieutenant A. S. Gracewski, Chief Warrant Officer C. W. Meyer, Mr. C. R. Singman and Ms. S. L. Hoglind. . . . . The survey team first met on June 11, 1980. Captain Fallon testified that it started with "a negative attitude." In addition to an Appointment Letter, the team was given copies of Federal Procurement Regulations, Defense Acquisition Regulations, a portion of Department of Transportation Regulations and a Department of Defense preaward survey form number 1524, Appendix K to the Defense Acquisition Regulations (DAR) and Navy Regulations referred to as SACAM. The team understood that it was to comply with the Federal Procurement Regulations and that the other regulations and the Form 1524 were given to them for guidance only. The purpose of the survey was to determine whether or not Plaintiff could obtain the necessary resources to construct the cutters, in view of the fact that it had not previously performed a contract of this magnitude, did not have either personnel or facilities necessary to perform the contract and because it had but recently acquired the use of a site in Coddington Cove, on the west shore of Aquidneck Island, upon property which had become surplus from the United States Naval Base, Newport, Rhode Island. The team forwarded a telegraphic request to Plaintiff of the information it would require for the survey and arrived at the site on Monday, June 16. The survey information was obtained over a period of five days, and the team returned to Washington, D. C. on Friday, June 21. In general, the survey team investigated the Plaintiff's ability to obtain plant facilities and equipment, personnel and financing for the performance of the contract. The specific categories studied were Production Capability, Plant Facilities and Equipment, Financial Capability, Purchasing and Subcontracting, Accounting System, Quality Assurance Capability, Transportation, Plant Safety, Security, Labor Resource, Performance Record, Ability to Meet Required Schedule and Management. In sum, the survey award team's report submitted on July 10, 1980, found that Plaintiff did not then have the capability to meet the contract requirements since it had little production capability and virtually no management or administrative capability at the time of the survey. In spite of Plaintiff's lack of facilities and personnel, however, "the Survey Team unanimously determined that Robert E. Derecktor of Rhode Island, Inc. has adequately provided acceptable evidence of his (sic) ability to obtain equipment, facilities and personnel needed to comply with the contract requirements." The Chairman, Captain Grabb, stated: a. A suitable line of credit is available from the consortium headed by the Hospital Trust Bank. A commitment from the bank was promised but never received. b. The drydock LIONEL FORSYTH is suitable for launching the 270 WMEC. Evidence to satisfy this requirement should be in the form of a written commitment by R. E. Derecktor (sic) to accomplish whatever repairs are deemed necessary by an independent competent marine surveyor. c. The current strike will be satisfactorily resolved."
The contracting officer, after reviewing a cash flow projection submitted by Marine's expert relating to Plaintiff's performance of the contract, awarded the contract to Plaintiff on January 15, 1981. Thereupon, both Marine and Tacoma sought an order of this Court enjoining performance of the contract pending a determination of the responsibility of Derecktor, and a determination of whether the Coast Guard had complied with applicable laws and regulations. On February 3, 1981, this Court enjoined the Coast Guard from executing the contract until the conclusion of trial on the merits and on March 2, 1981, the Court ordered the injunction to continue until decision. . . . . In general, Intervenors argue that the action of the Contracting officer in his award of the contract to Plaintiff on January 15, 1981, was irrational or unreasonable in that this action was the award of the largest Coast Guard contract in its history and was made to Plaintiff solely on the basis of its perceived estimate of Plaintiff's ability to perform the contract. Central to this argument is the fact that Plaintiff does not now have a shipyard capable of performing the contract and has not previously built ships of the size and number required by the contract. Intervenors question Plaintiff's financial ability and assert that Plaintiff is not capable of performing the contract within either the bid price or the time limitations stated in the contract. Additionally, Intervenors contend that performance of the contract will be delayed because the Coast Guard first must comply with the requirements of NEPA before awarding the contract. Specifically, Intervenors argue that the award was in fact made to two companies, Robert E. Derecktor of Rhode Island, Inc. and Rhode Island Shipbuilders, Inc.; that Rhode Island Shipbuilders, Inc. has not been determined to be a responsible bidder, and, therefore, that the award is invalid. They argue that although the bid submitted by Plaintiff in June of 1980 provided for delivery of the first completed vessel in thirty months, the Coast Guard permitted the bid to be modified to comply with bid specifications after submission but before acceptance to require delivery of the first vessel in thirty-six months.[FN2] Intervenors presented testimony from two experts: Ted Frost, a C.P.A., and Marvin Miller, a retired Government Procurement Specialist. Apart from the basis for their opinions, the testimony of Mr. Frost is seriously flawed by the fact that he and his firm performed accounting services for Intervenor Marine Power for the past eleven years, and the testimony of Mr. Miller was similarly suspect because of his almost concurrent efforts to arrange a procurement contract for Plaintiff which could not be simultaneously accomplished. Mr. Frost's ultimate opinion was that Plaintiff's and the Coast Guard's cash flow projections were not made on a "worst case" basis and that in fact a proper cash flow analysis would require not only twice the amount of financing available to Plaintiff but that the type of financing available to Plaintiff, based upon advances of up to eighty percent of receivables, was inappropriate. Mr. Miller testified, in sum, that the contracting officer did not have sufficient data available to him to determine that Plaintiff was a responsible contractor. Intervenors contend on the basis of Mr. Frost's testimony, that the Coast Guard erred with respect to the time of receipt of payment for work performed under the contract with respect to all vessels to be constructed after the first vessel with the result that at month thirty-six of the performance of the contract based on the Coast Guard figures and assumptions, Plaintiff would need almost thirty million dollars of financing, while it had only inadequately provided for a little more than fifteen million dollars. It also contended, based upon Mr. Frost's testimony, that the cash shortage which would exist at month thirty-six would be not less than thirty million dollars and actually could amount to almost forty million dollars. Based upon the fact that Plaintiff's line of credit amounts to fifteen million dollars, Intervenors contend that it will be financially impossible for Plaintiff to perform the contract and that the Plaintiff will default with consequent delay and damages to the Coast Guard. Plaintiff, on the other hand, contends that Mr. Frost did not take into consideration the possibility that Plaintiff's vendors would require payment from Plaintiff only after Plaintiff received payment from the Coast Guard. A cash flow projection for a project to be accomplished is at best an informed prediction, the accuracy of which can be finally determined only after the project has been completed. Having in mind that it is a prediction and the fact that the Coast Guard personnel who participated in the survey has already had some actual experience with the ongoing construction expenses of its Class A 270 foot medium endurance cutters by Intervenor Tacoma, and that Intervenor's witness, Mr. Frost, not only has a bias but is completely lacking experience of the specific type possessed by the Coast Guard personnel, it is more likely than not that the Coast Guard is not in error in its prediction of cash flow. Intervenors have failed to prove that a financial debacle is likely to result so that it can be said that the determination of the Coast Guard represents either a serious mistake or bad business judgment, much less an unreasonable or irrational determination. When bids are advertised, "(a)ward shall be made ... to that responsible bidder whose bid, conforming to the Invitation For Bids, will be most advantageous to the Government, price and other factors considered." 41 U.S.C. s 253(b). The General Services Administration (hereinafter GSA) has issued Federal Procurement Regulations (hereinafter FPR) [FN3] that set forth standards for determining responsibility and specifically require the contracting officer to make an affirmative determination that the prospective contractor is responsible before a contract is awarded. 41 C.F.R. s 1- 1.1204-1. Both Marine Power and Tacoma seek to have this Court overturn the affirmative determination of responsibility made by the Coast Guard contracting officer in awarding the contract to Plaintiff. Before addressing this issue, it is necessary to consider whether judicial review of an affirmative determination of responsibility is appropriate and, if so, the standard of review to be applied. FN5. Intervenors have cited many procurement cases in support of their contention, including M. Steinthal & Co. v. Seamans, 455 F.2d 1289 (D.C.Cir.1971), and Merriam v. Kunzig, 476 F.2d 1233 (3d Cir. 1973). . . . . The courts that have permitted judicial intrusion into the procurement process have not essentially concerned themselves with whether or not the agency decision was correct but whether or not the agency decision was correct but whether or not the agency acted legitimately, certainly a more appropriate judicial consideration. There is no question of the direct interest of the parties to this action in assuring that the agency decision was within the authority vested in the agency. In Hahn, the court considered a rather specific statutory "carte blanche," given to the Secretary of HUD, [FN6] and the court held that Congress meant what it said. The FPR, on the other hand, are not outright Congressional grants of authority but are promulgated under the Federal Property and Administrative Services Act of 1949. That Act provides that "(t)he Administrator shall prescribe such regulations as he deems necessary to effectuate his functions under this Act, and the head of each executive agency shall cause to be issued such orders and directives as such head deems necessary to carry out such regulations." 40 U.S.C. s 486(c). Moreover, the FPR establish a considerable number of benchmarks all of which must be traversed in order to exercise the ultimate decision of whether or not to commit substantial public monies to the acquisition of public property. Those decisions which have allowed limited excursions into the procurement process have sought an accommodation. They profess considerable latitude for procurement decisions, but not a total dispensation in terms of unfettered determinations, at least to the extent of requiring compliance with the regulatory process. That is to say that they involve not whether the Administration decision is correct, but whether the decision correct or not was arrived at in compliance with the regulatory process. To this extent Hahn and the opinions which sanction review can be harmonized. A judicial requirement that the agency comply with the regulatory process safeguards the interest of the public and the parties, and it could be argued with some vigor and conviction that the impact of review so limited is likely to provoke more public benefit than the alternative of total abdication. Thus, the Court concludes that Hahn does not preclude a limited inquiry.[FN7] Some courts have stated that the absence of a rational basis may be demonstrated by a clear and prejudicial violation of applicable statutes or regulations in the procurement procedure. General Electric Co. v. Kreps, 456 F.Supp. 468, 472 (D.D.C.1978) (quoting Kentron Hawaii, Limited v. Warner). See also Tidewater Management Services, Inc. v. United States, 573 F.2d at 67. Other courts, however, have treated proof of statutory and regulatory violations as a separate consideration from that which analyzes whether a rational basis exists. E.g., Kentron Hawaii, Limited v. Warner, 480 F.2d 1166 (D.C.Cir.1973).[FN10] It is well settled, moreover, that contracting officers have wide discretion in determining a bidder's responsibility.[FN11] Tidewater Management Services, Inc. v. United States, 573 F.2d at 73; Keco Industries, Inc. v. United States, 492 F.2d at 1205; See also Old Dominion Dairy Products, Inc. v. Secretary of Defense, 631 F.2d 953, 960 (D.C.Cir.1980) (contracting officers have wide discretion in determining nonresponsibility). As the Court of Claims noted in Trilon Educational Corp. v. United States, "responsibility 'determinations are based in large measure on subjective judgments which are not readily susceptible to reasoned review.' " 578 F.2d 1356, 1358 (Ct.Cl.1978) (quoting Data Test Corp., 54 Comp.Gen. 499 (1974)). Nonetheless, such review has not been foreclosed. The burden of successfully disputing a contract award is necessarily a heavy burden. Otherwise, the judgment of courts could be substituted for those of procurement officials, destroying an elaborate and technical procurement process and effectively substituting the decisions reposed by law and regulation in the procurement process in contracting officers with a judicial determination that the Executive Branch of Government could have made "a better deal." Furthermore, as this action so well illustrates, with the strictures of procurement regulations, the decision of who is a responsible bidder is essentially a question of business judgment which any unsuccessful bidder may contest, with consequent delay and cost to the Government. Review of the procurement decision is a task not to be undertaken lightly and a contrary judicial determination should be made only in the clearest case. The possibilities are numerous, once the decision is made, to take a "peek" at the procurement process. Doubtless, procurement decisions are made daily, involving large expenditures by Government agencies. Disappointed bidders would be encouraged to delay and impede procurement contracts in the hope that something will happen to their advantage at the courthouse steps. This type of bargaining is antithetical to the bidding process. If permitted without limitation, the most persuasive argument would be substituted for the lowest responsible price. Turning to the present controversy, the decision to award this contract was made by a contracting officer who relied heavily upon the recommendations of the survey team. See 41 C.F.R. s 1-1.1205-4 (contracting officer shall use preaward survey as aid in determining responsibility). See also 41 C.F.R. s 1-1.1205-1 ("contracting officer shall have ... information sufficient to satisfy himself ... that prospective contractor meets ... minimum standards ...."). There is not the slightest suggestion of either bad faith on the part of the procuring officials or a clear and prejudicial violation of relevant statutes or regulations. It is true that upon analysis some aspects of the determinations might be subject to debate, particularly since the determination was made on the basis of the ability of the Plaintiff, as yet unproved, to perform the contract. 41 C.F.R. s 1-1.1203-4 (Regulation governing ability to meet certain minimum standards). It is a question of informed judgment whether Plaintiff can create the facilities, provide the personnel and necessary equipment and perform the work within the time and price of its bid. But, in the last analysis, it is a judgment which must be committed to the procuring officials. In this instance, they are not without experience and it is not suggested that they lack the necessary sophistication to make such a determination. The expertise of the survey team relied upon by the contracting officer is not only beyond question, but it has not been questioned. Turning to specific criticisms by Intervenors, the contention that the award was made to Rhode Island Shipbuilders, Inc., clearly not a responsible bidder, is too technical to merit serious consideration since the award was also made to Robert E. Derecktor of Rhode Island, Inc. The conjunction of Rhode Island Shipbuilders, Inc. and Robert E. Derecktor of Rhode Island, Inc. does not in any way diminish the validity of the responsibility determination concerning Robert E. Derecktor of Rhode Island, Inc. The validity of the award depends only on a finding that there is one responsible bidder. Intervenors contend that because the analysis of Plaintiff's responsibility depends entirely on Plaintiff's future ability to perform without a present capacity to do so, it must demonstrate the present availability of equipment to be acquired, timely and workable production, management accounting and quality assurance programs, compliance with industry regulations, including OSHA, labor force and the ability to launch completed vessels, and bonding and insurance contracts. Intervenors would have the Court infer from the record that Plaintiff cannot perform the contract within the time and price limitations of the contract. This alleged inability to perform the contract must be inferred because Intervenors have presented no direct evidence in support of their contention. The principal contrary consideration is that the survey team, composed of the more senior, experienced Coast Guard personnel, came to the opposite conclusion and its recommendation was accepted by the contracting officer. The regulations required that the contracting officer make an affirmative determination that the prospective contractor is responsible with respect to the contract. 41 C.F.R. s 1-1.1204-1(a). The conclusion was reached by the Coast Guard based upon its understanding of the applicable procurement regulations. And, there is no evidence that the Coast Guard did not act in good faith. The Court is thus asked to find a good faith determination of the Coast Guard, based upon expertise and experience, to have been wrong. There is no evidence of either a clear or prejudicial violation of any particular regulation and there is no evidence that any particular applicable regulation was overlooked. Intervenors are particularly critical of the lack of contracts between Plaintiff and its subcontractors and suppliers. Their argument, in part, is that without agreements in existence at the time of the bid submission, there can be no assurance of timely performance or of price. See 41 C.F.R. s 1- 1.1203-1 (prospective contractor must be able to comply with required or proposed delivery or performance schedule). There is no direct evidence that Plaintiff cannot perform this contract or that it will default. The contracting officer received evidence which, however incomplete, was acceptable to him and may well have determined that the "normal" requirement for commitment or explicit arrangement was not to be applied in this instance. The regulations do not require contracts with subcontractors or suppliers as essential to a responsible bid. See also 41 C.F.R. s 1- 1.1206(a) (determinations of responsibility of prospective subcontractors "generally ... made by the prospective prime contractor" and prospective prime contractor may be required to (1) provide written evidence regarding responsibility of proposed subcontractors, or (2) demonstrate effective purchasing and subcontracting system"). Intervenors seek to impose too high a degree of certainty in the bidding process which would have all the aspects of the performance of the bid "cast in stone." They would ignore the possibility that a contractor may chose to negotiate with subcontractors and suppliers after the award of the contract, and that the prime contractor of a fixed price contract has the risk of financial loss. Under the award, the contractor is to receive progress payments based upon percentage of completion, as agreed to by the Coast Guard and the prime contractor. The risk to the Government is minimal, since it pays only for what it gets. Thirty-eight percent (38%) of the dollar cost of this contract is to be provided by subcontractors. A substantial portion of these items are to be provided by "sole source " supplier; that is, the Coast Guard has designated the only supplier of the item. These items include electronics and fire control equipment and various items of the propulsion equipment. There is no evidence that even one essential element required by the contract is not available. And, returning to the fundamental finding, which has not been impeached, the Coast Guard is satisfied that the work can be done. The evidence is that the determination to award the contract to Plaintiff is neither arbitrary nor capricious, that it was made in good faith, that the determination did not lack a reasonable or rational basis, and that there was no clear and prejudicial violation of any procurement regulation. . . . . This Court holds, therefore, that Plaintiff is a responsible bidder and that the award of the procurement contract to Plaintiff is valid and in accord with the procurement regulations. Plaintiff's Motion to Dismiss is denied, and the preliminary injunction entered on February 3, 1981, is vacated and the prayer for permanent injunctive relief is denied. SO ORDERED. APPENDIX 5. Robert E. Derecktor of Rhode Island, Inc. (RED) does not currently have the capability to accomplish the work required to meet the contract requirements. The Rhode Island facility surveyed has very little production capability and virtually no management and administrative capability at this time. In almost all areas examined, existing capabilities are unsatisfactory. As a result, the survey team evaluated the prospective contractor's ability to obtain the necessary resources. 6. The Survey Team inspected the RED facility, and interviewed Mr. Robert Derecktor, key personnel now employed or planned to be employed by Mr. Derecktor, major prospective subcontractors, and local government officials. Mr. Derecktor is a boat/ship builder of long standing and has completed other Coast Guard, government and commercial contracts at another shipyard successfully. However, none of the previous contracts required the productive capacity, logistics, or management expertise as the contract this survey pertains to. Under intense inquiry by the Team, Mr. Derecktor and his very limited staff displayed an adequate understanding of the contract requirements and an ability to assemble the resources (personnel and facility) needed to produce the cutters on time and within the price bid. Their plans both to upgrade the facilities and to provide labor resources are viable. 7. The prospective contractor is currently receiving substantial government help. The property is under sublease from the State of Rhode Island who has a lease with the U. S. Government. The terms are extremely favorable to RED. In addition, he has received a low interest loan from the State of Rhode Island for additional facilities and equipment. The State also plans to operate a training school (CETA) on-site at the shipyard to provide entry level skilled personnel. A similar CETA funded training facility has been used at the Electric Boat plant at Quonset Point where Trident submarines are being fabricated. I was told by Navy personnel that the school is very effective. Governor Garrahy appeared before the Survey Team and pledged full State support should Derecktor be awarded the contract. 8. Derecktor has requested that
he be allowed to deliver the first vessel in 36 months rather than the
30 months he proposed with his bid. During the Survey, Derecktor presented
evidence showing that 36 months is required. |
|
|