|
|
| 412
F.2d 1215 188 Ct.Cl. 620 GENERAL ELECTRIC
COMPANY, a Corporation Before COWEN, Chief Judge, and LARAMORE, DURFEE, DAVIS, COLLINS, SKELTON, and NICHOLS, Judges. COLLINS, Judge. In the court's view of this case, the main issue for decision is whether, under the Limitation of Cost article [FN1] included in the instant cost-plus-fixed-fee contract, a contracting officer effectively exercised his discretion in favor of allowing overrun costs to the contractor, after General Electric failed to timely notify the Government of the overrun. '(a) It is estimated that the total cost to the Government, exclusive of any fixed fee, for the performance of this contract will not exceed the estimated cost set forth in the Schedule, and the Contractor agrees to use his best efforts to perform the work specified in the Schedule, and all obligations under this contract within such estimated cost. If at any time the Contractor has reason to believe that the costs which he expects to incur in the performance of this contract in the next succeeding sixty (60) days, when added to all costs previously incurred, will exceed seventy-five percent (75%) of the estimated cost then set forth in the Schedule, or if at any time, the Contractor has reason to believe that the total cost to the Government, exclusive of any fixed fee, for the performance of this contract will be substantially greater or less than the then estimated cost thereof, the Contractor shall notify the Contracting Officer in writing to that effect, giving the revised estimate of such total cost for the performance of this contract. '(b) The Government shall not be obligated to reimburse the Contractor for costs incurred in excess of the estimated cost set forth in the Schedule, and the Contractor shall not be obligated to continue performance under the contract or to incur costs in excess of the estimated cost set forth in the Schedule, unless and until the Contracting Officer shall have notified the Contractor in writing that such estimated cost has been increased and shall have specified in such notice a revised estimated cost which shall thereupon constitute the estimated cost of performance of this contract. When and to the extent that the estimated cost set forth in the Schedule has been increased, any costs incurred by the Contractor in excess of such estimated cost prior to the increase in estimated cost shall be allowable to the same extent as if such costs had been incurred after such increase in estimated cost. (ASPR 7--402.2, Feb. 1959)' As provided at page 2 of Appendix A of the contract, primary supervision and administration was delegated to the Boston Procurement District, [FN3] with technical supervision reserved to the Army Weapons Command. Although nothing in the agreement specifically contemplated it, the Command also retained funding authority. 'All activity pertaining to the technical aspects of this project will be under the technical supervision of the Project Engineer, Mr. Steve Thodos, Rock Island Arsenal, Rock Island, Illinois. All other administration is the responsibility of the Contracting Officer, Boston Procurement District, U.S. Army. Changes in the scope of work shall be effected only by the Contracting Officer, by properly executed modifications to the contract. * * *' The person in the Government with whom plaintiff actually dealt (through its contract administrator, Mr. Aldrich) was a Mr. John Petze. Titled a 'contract specialist,' Mr. Petze had no authority to modify the contract, but acted only as a Government contact for General Electric, as plaintiff was aware. [FN4] Plaintiff did not stop work on the contract when it became aware of the overrun, and concededly incurred its additional costs prior to notifying defendant in writing. The board suggests that plaintiff's failure to stop work was partly because both plaintiff and defendant considered the contract performance urgent. However, the board considered it likely that General Electric was motivated primarily by a desire to obtain the production contract which would naturally flow from the successful completion of the research and development performance. Plaintiff's claim is predicated upon the correspondence between the Boston Procurement District and the Army Weapons Command subsequent to General Electric's notice of September 1964. On October 2, 1964, Mr. Whalley, a contracting officer's representative and Mr. Petze's superior, wrote to the Army Weapons Command concerning the availability of funds for modification of the contract by reason of the overrun. Mr. Lindblad, who, as previously mentioned, was funding contracting officer for the Command, replied on October 22, 1964, requesting investigation and justification of the contractor's claim in terms of the Limitation of Cost article. In January 1965, Government representatives investigated the overrun and found the costs stated in plaintiff's submission to be reasonable. On March 9, 1965, Mr. Whalley again wrote the Command, stating that the additional costs were justified on the basis of Government analyses and recommending funding of the overrun. The reports of the investigators were included. On June 7, 1965, the Army Weapons Command wrote asking several questions about the overage. By letter of June 30, 1965, the Boston Procurement District answered the questions and stated the legal opinion that neither advance notice nor a request for continued work was mandatory to the funding of the overrun. The letter concluded as follows: FOR THE COMMANDER: /s/ Sumner A. Marcus
CONCUR WITH RECOMMENDATION: /s/ R. F. McDermott
Plaintiff argues that the concurrence of Lieutenant Colonel McDermott in the letter of June 30, 1965, signed by Mr. Marcus, was an effective decision by a contracting officer that plaintiff was entitled to its additional overrun costs. [FN5] We agree. In denying plaintiff's appeal and motion for reconsideration, the board, whether in reliance upon testimony that Colonel McDermott had authority only up to $10,000 or upon the administrative framework, found that a contracting officer at the Boston Procurement District did not have authority to fund an overrun without the approval of the Army Weapons Command. It also found that Colonel McDermott's recommendation could not amount to a contracting officer's decision. Defendant has conceded in its reply brief before the court, however, that the testimony before the board concerning the colonel's monetary authority was in error, and that in fact he was empowered to handle matters involving amounts up to $1,000,000. This concession makes it clear that if was unnecessary for Colonel McDermott to resort to the Army Weapons Command for authority to fund the overrun. He had already been delegated the necessary power. However desirable it seemed to the Command to retain all funding responsibility, by the Army's delegation of monetary authority to the colonel and by the Command's failure to somehow limit that authority with respect to the instant contract, through inclusion of a specific provision or otherwise, the Army Weapons Command did not reserve all control over funding. Under the facts of this case, the internal administrative scheme whereby the Boston Procurement District was to defer to the Army Weapons Command concerning funding cannot diminish Colonel McDermott's authority. His grant of authority can only be properly viewed as permitting an exception to the expected practice. The board holding or finding to the contrary is in error as a matter of law. The question which remains is what legal effect is to be given to the concurrence of Colonel McDermott in the recommendation of the chief legal officer under the instant circumstances. The evidence before the board showed conclusively that the Boston Procurement District from the first official *1221 notification of the overrun consistently expressed the opinion that General Electric was entitled to reimbursement for its additional costs. It was therefore not unlikely that Colonel McDermott was acquainted with the facts underlying the overrun dispute. [FN6] Whether he was aware of the situation prior to June 30, 1965, it seems clear that, as a responsible Government official, he would have duly investigated the matter before indicating his concurrence, as contracting officer, in a recommended course of action. Failure to do so before signing in an official capacity would have been neglect of duty. Unless evidence to the contrary is produced, the law presumes that official actions are properly taken. See Biddle v. United States, 186 Ct.Cl. 87, 104 (1968); Holman v. United States, 383 F.2d 411, 181 Ct.Cl. 1 (1967); Harrington v. United States, 161 Ct.Cl. 432 (1963). Defendant also contends that Colonel McDermott had no authority with respect to the instant contract, citing our decisions in New York Shipbuilding Corp. v. United States, 385 F.2d 427, 180 Ct.Cl. 446 (1967), and Climatic Rainwear Co. v. United States, 88 F.Supp. 415, 421, 115 Ct.Cl. 520, 558--559 (1950). Those cases stand for the proposition that where the parties to a Government contract agree that a certain official shall determine disputed factual matters between them, this fact-finding authority cannot be delegated or exercised by someone else. In the instant case, however, no specific individual was designated as contracting officer. See footnote 3, supra. As previously mentioned, contract documents in this case were executed by several different contracting officers for the Boston Procurement District. In these circumstances, we cannot find that Colonel McDermott was without authority with respect to plaintiff' contract, and the cited cases are inapposite. We find, therefore, that Colonel McDermott was aware of the overrun situation and his indication of concurrence meant exactly what it said: that he, as contracting officer, approved the funding of the overrun and favored reimbursing plaintiff for its costs. Under the facts present here, we believe that when an authorized contracting officer expresses a definite opinion concerning the merits of a claim with knowledge of the relevant facts, a 'decision' has been made. As we have emphasized numerous times, it is the unfettered opinion of the person delegated as decision-maker by the parties to the contract that is determinative. E.g., New York Shipbuilding Corp. v. United States, 385 F.2d 427, 180 Ct.Cl. 446 (1967) (and cases cited); John A. Johnson Contracting Corp. v. United States, 132 F.Supp. 698, 132 Ct.Cl. 645 (1955). Thee is no evidence in this record that Colonel McDermott was not expressing his own opinion when he concurred in Mr. Marcus' recommendation. Cf. John A. Johnson Contracting Corp. v. United States, supra. Accordingly, the decision of a duly authorized contracting officer could not be defeated by a funding official at the Army Weapons Command. Nor, by implication, could Colonel McDermott's finding be reversed by a successor contracting officer. See Climatic RainwearCo. v. United States, 88 F.Supp. 415, 115 Ct.Cl. 520 (1950). Mr. Lindblad's determination of September 1966 was therefore a nullity. [FN7] Plaintiff's motion for summary judgment is granted in accordance with this opinion, and defendant's cross-motion is denied. Judgment is entered for plaintiff in the amount of twelve thousand eight hundred and eighty-eight dollars ($12,888). NICHOLS, Judge (dissenting): Respectfully I regret
to be unable to agree with the foregoing decision. I do not know whether
any purely intra-government document, not communicated to the contractor,
can be a notification to the contractor as the contract contemplated.
I think that is indeed questionable. But if any writing is such a notification,
I think it can only be such if it purports to be such. The writing here
relied on purports simply to be advice to other Government officials.
The commitment of the Government to reimburse for cost overruns is a
serious matter and involves the control of expenditures by Congress
and by fiscal officials. I would not knowingly do anything to weaken
that control. The amount here involved is small, as Government contract
expenditures go, but the principle is large. |
|
|